Chicago began work on a two-phase concourse that will add international gates, link to the new Concourse D by tunnel and finish in 2034 alongside the $8.7 billion Global Terminal.

By The Touch & Go EditorialPublished Nov 17, 10:45 PM2 min read

The gist

Chicago broke ground on O'Hare's $917 million Concourse E, a 24-gate project due in two phases by 2030 and 2034.

Chicago officials broke ground Tuesday on Concourse E at O'Hare International Airport, a $917 million project that will add 24 gates at Terminal 2, including more gates for international flights. Mayor Brandon Johnson joined airline leaders at the airport for the ceremony. The concourse will be built in two phases over the next eight years. It is one of three linked construction projects that together will give O'Hare its largest terminal expansion on record.

The first phase carries a $640 million price tag and is scheduled for completion in 2030. It will deliver 14 gates and nearly 21,000 square feet of concessions space for shops and restaurants. That phase also includes an underground tunnel connecting Concourse E to the new Concourse D. Concourse D is already under way and is scheduled to open in 2028, two years ahead of the first section of Concourse E.

The second phase, budgeted at $277 million, will add the remaining 10 gates. Its timeline depends on the airport's largest project, the $8.7 billion O'Hare Global Terminal. The city expects the Global Terminal to be finished in 2033, with the second phase of Concourse E following in 2034. The sequencing means the final gates on the concourse will open roughly a year after the new terminal they will serve.

The O'Hare Global Terminal will cover 2.2 million square feet and will replace the existing Terminal 2. Concourse E is being built at the same terminal site, which is why its later phase waits on the Global Terminal. Once Concourse D, Concourse E and the Global Terminal are all complete, O'Hare's gate capacity will rise by 14%. City officials said that makes the combined program the biggest terminal expansion in the airport's history.

Johnson said O'Hare serves more than the city alone and that the project will strengthen Chicago's position in the global economy. He said the real return on the spending would be measured in the jobs created, the businesses supported, the career paths opened and the opportunities made available to Chicago families. Airline leaders attended the groundbreaking alongside the mayor.

The terminal designs now being built also account for growth beyond the current program. Officials said the layouts of the ongoing O'Hare projects anticipate future expansion of the airport, leaving room to add capacity after the 2034 completion date for Concourse E.

Originally reported by CBS News

Share

The Daily Touch & Go

The day's best aviation news in your inbox. Free, no spam.